Milltown Residential Complex

The construction company Monolit Bau operates as the General Contractor and is erecting (or constructing) buildings No. 3, 5, 6, 7 and the Trade and Office Center (or Commercial and Office Center).
Residential Complex "Milltown" Building No. 3
In January 2021, the construction company Monolit Bau began the construction of Building No. 3 and performed the following works:
  • Excavation and Foundation Works
    The work performed is:
    1. Installation of a crushed stone and sand sub-base 10 cm thick.
    2. Laying a concrete blinding layer (10 cm thick).
    3. Pouring foundation slabs totaling 675 m3.
  • Erection of the walls for Building No. 3
    The following works were completed:
    • Building frame exceeding 2,500 linear meters.
    • Installation of 15 stair flights.
    • Installation of interior walls exceeding 1,275 m3.
    • Installation of partitions exceeding 5,850 m3.
  • Completion of Building No. 3
    The construction of the facility began in January 2021, commissioned by Integral-Bud LLC (TOV "Integral-Bud"). All work is being carried out in compliance with the design documentation and all building codes and standards. In 2022, the building, with a total area of 5,369 m2, was commissioned (or put into operation).
Residential Complex "Milltown" Building No. 5
In February 2021, the construction company Monolit Bau began the construction of Building No. 5 and performed the following works:
  • Ground and Foundation Construction
    Installation of a crushed stone and sand sub-base.
    Laying a concrete blinding layer (10 cm thick).
    Pouring of foundation slabs (using C20/25 concrete).
  • Erection of the walls for Building No. 5
    Building Frame
    Installation of Stair Flights
    Installation of Interior Walls
    Installation of Partitions
  • Completion of Building No. 5
    The construction of the facility began in February 2021, commissioned by Integral-Bud LLC (TOV "Integral-Bud"). All work is being carried out in compliance with the design documentation and all building codes and standards. The building was commissioned (or put into operation) in 2022.
Residential Complex "Milltown" Building No. 6
In November 2021, the construction company Monolit Bau began the construction of Building No. 6 and performed the following works:
  • Ground and Foundation Construction
    The following foundation works were performed:
    • Installation of a crushed stone and sand sub-base.
    • Laying a concrete blinding layer (10 cm thick).
    • Pouring of foundation slabs (using C20/25 concrete).
  • Construction of the walls for Building No. 6
    Building Frame construction.
    Installation of stair flights.
    Installation of interior walls.
    Installation of partitions.
  • Construction of the walls for Building No. 6
    The construction of the facility began in February 2022, commissioned by Integral-Bud LLC (TOV "Integral-Bud"). All work is being carried out in compliance with the design documentation and all building codes and standards. The building was commissioned (or put into operation) in 2023.
Residential Complex "Milltown" Building No. 7
In February 2022, the construction company Monolit Bau began the construction of Building No. 7 and performed the following works:
  • Ground and Foundation Construction
    Installation of a crushed stone and sand sub-base.
    Laying a concrete blinding layer (10 cm thick).
    Pouring of foundation slabs (using C20/25 concrete).
  • Construction of the walls for Building No. 7
  • Completion of Building No. 7
    The construction of the facility began in February 2022, commissioned by Integral-Bud LLC (TOV "Integral-Bud"). All work is being carried out in compliance with the design documentation and all building codes and standards. The building was commissioned (or put into operation) in 2023.
MillTown Shopping Center
In June 2023, the construction company Monolit Bau began the construction of the MillTown Shopping Center (or MillTown Commercial Center) and performed the following works:
  • Ground and Foundation Construction
    Installation of a crushed stone and sand sub-base.
    Laying a concrete blinding layer (10 cm thick).
    Pouring of foundation slabs (using C20/25 concrete).
  • Wall Construction
    Building Frame
    Installation of Stair Flights
    Installation of Interior Walls
    Installation of Partitions

Complex of completed works

  • Soil preparation for construction

    Vegetation Removal, Site Clearance, Waste Disposal, and Foundation Preparation Before Construction
  • Excavation of the foundation pit

    Laying the Crushed Stone and Sand Sub-base for the Foundation (or Formation of the Aggregate-Sand Base for the Foundation)
  • Concreting of the foundation

    Before pouring the foundation, our workers carry out preparatory works, and once it achieves sufficient strength, they begin the erection of monolithic-frame structures (or reinforced concrete frame structures)..
  • Construction of monolithic-frame structures

    Monolithic-Frame Construction and Installation Services

  • Foundation waterproofing

    To protect the foundation from moisture and deterioration, foundation waterproofing is carried out.
  • Masonry of walls and partitions

    For the construction of walls and interior partitions on the site, the following materials were used: solid brick M-100, ceramic block 2-12-NF (or Porotherm 2-12 NF), and autoclaved aerated concrete (AAC) block (or gas block).
  • Laying of engineering networks

    Installation of internal engineering utilities, including heating supply networks, water supply networks, drainage/sewerage systems, and general pipeline installation.

  • Facade works

    Facade works. The quality of external finishing works determines not only the beauty of the building but also its durability and energy-saving properties.

Construction companies are the driving force of city development.

Construction companies in Lviv are the true creators. The comfort of every resident depends on them, because while architects and designers conceptualize, we take on the role of the one who transforms the concept into reality. And this is not easy. The project visualization hides the entire physical process—from pouring the foundation to laying power lines. For the construction 'anthill' to work seamlessly, it requires a comprehensive approach and centralized control over every stage.

Our contacts

Lviv, Shevchenko street 60 / 9

Phone: +380 67 699 51 81

Mail: a.bulah@gmail.com