"Shengen" Residential Complex

The construction company Monolit Bau has completed the construction of Building No. 11 in the "Shengen" Residential Complex.
Shengen RC, Building 11
In September 2020, the construction company Monolit Bau began the construction of Building No. 11 and performed the following works:
  • Ground and Foundation Construction
    Concrete pouring of the foundation. After the preparatory work is carried out, the first stage in construction is the concrete pouring of the foundation. Once the monolith solidifies and gains strength, construction work can proceed, allowing for the erection of walls and the frame, as well as the application of foundation waterproofing.
  • Construction of the walls for Building No. 11
    The following works were completed:
    1. Installation of the building frame (or Structural frame erection).
    2. Installation of stair flights.
    3. Installation of walls and partitions.
  • Completion of Building No. 11
    The construction of the facility began in September 2021, commissioned by RIEL LLC (TOV "RIEL"). All work is being carried out in compliance with the design documentation and all building codes and standards. The building was commissioned (or put into operation) in 2022.

Complex of completed works

  • Soil preparation for construction

    Vegetation Removal, Site Clearance, Waste Disposal, and Foundation Preparation Before Construction
  • Excavation of the foundation pit

    Laying the Crushed Stone and Sand Sub-base for the Foundation (or Formation of the Aggregate-Sand Base for the Foundation)
  • Concreting of the foundation

    Before pouring the foundation, our workers carry out preparatory works, and once it achieves sufficient strength, they begin the erection of monolithic-frame structures (or reinforced concrete frame structures)..
  • Construction of monolithic-frame structures

    Monolithic-Frame Construction and Installation Services

  • Foundation waterproofing

    To protect the foundation from moisture and deterioration, foundation waterproofing is carried out.
  • Masonry of walls and partitions

    For the construction of walls and interior partitions on the site, the following materials were used: solid brick M-100, ceramic block 2-12-NF (or Porotherm 2-12 NF), and autoclaved aerated concrete (AAC) block (or gas block).
  • Laying of engineering networks

    Installation of internal engineering utilities, including heating supply networks, water supply networks, drainage/sewerage systems, and general pipeline installation.

  • Facade works

    Facade works. The quality of external finishing works determines not only the beauty of the building but also its durability and energy-saving properties.

Construction Company Monolit Bau — Build with us!

We offer turnkey construction, which includes high-quality execution of all stages and strict control over our team's work. We also easily integrate into an ongoing work process, quickly completing a specific task before passing the baton to the next stage. We are easy to work with.
Monolit Bau is a construction company whose home city is Lviv. However, we strive to implement successful ideas across all of Ukraine. And we succeed, because only developers from Lviv—a city with complex infrastructure, landscape, and architectural requirements—are truly capable of integrating into the challenging environments of other cities.

We don't build hypotheses; we create modernity.

Our contacts

Lviv, Shevchenko street 60 / 9

Phone: +380 67 699 51 81

Mail: a.bulah@gmail.com